A bill of material must be updated with the corrected dimensions of a part. The document that details this change is a(n)

A) modular bill.
B) engineering change notice.
C) resource requirements profile.
D) lead time-offset product structure document.
E) planning bill.

Engineering Change Notice

A document that outlines modifications to a product's design or manufacturing process, usually initiated due to errors, improvements, or updates.

Bill Of Material

A comprehensive list detailing all the components and materials required to create a product.

Modular Bill

A document listing components or parts in a structured format that supports manufacturing or assembly of modular or customizable products.

  • Fathom the relevance and practice of renewing a Bill of Materials (BOM), and its effect on the production cycle.
verifed

Verified Answer

MF
Miguel FortunaMay 02, 2024
Final Answer :
B
Explanation :
An engineering change notice (ECN) is a document used to detail changes that need to be made to a product or process. In this case, the change is the corrected dimensions of a part in the bill of material. The ECN will communicate the change to the appropriate personnel and ensure that the updated information is implemented correctly.