In Scenario 16-2, the processes used in making various candies differ. Some candies are dipped, some are rolled in nuts, and some are layered. In determining the order with which various chocolates will go through the production system, Shana is considering which stage of the scheduling process?
A) routing
B) sequencing
C) dispatching
D) forward scheduling
Sequencing
The order in which the steps need to occur to produce a product.
Routing
The process of selecting paths in a network along which to send network traffic.
Dispatching
The process of sending out goods or deploying resources to a particular destination or for a specific task.
- Comprehend the scheduling process steps, including routing, sequencing, dispatching, and their significance.
Verified Answer
TM
Thurman MermanMay 03, 2024
Final Answer :
B
Explanation :
In this scenario, Shana is considering the sequencing stage of the scheduling process, which involves determining the order in which various chocolates will go through the production system. This is crucial for optimizing the production flow and meeting demand efficiently.
Learning Objectives
- Comprehend the scheduling process steps, including routing, sequencing, dispatching, and their significance.
Related questions
Sequencing Is the Critical Step in Determining the Order in ...
In Scenario 16-2, the Detailed Breakdown of Information Explaining Exactly ...
The Critical Ratio Sequencing Rule Prioritizes the Jobs Based on ...
Johnson's Rule Sequences a Set of Jobs Through Two Different ...
Dispatching Rules Are Typically Judged by Four Effectiveness Criteria: Average ...