Asked by ricardo Velazquez on May 07, 2024
Verified
In project management, crashing an activity must consider the impact on all paths in the network.
Crashing
Shortening activity time in a network to reduce time on the critical path so total completion time is reduced.
Network
A collection of interconnected devices or people that exchange data, resources, or communications.
- Acquire knowledge on tactics used to decrease the length of time required to complete a project, encompassing the idea of "project crashing."
Verified Answer
LP
Liberty PerryMay 14, 2024
Final Answer :
True
Explanation :
Crashing an activity may affect the duration of other activities and hence impact the critical path or other paths in the network. Therefore, it is important to consider the impact on all paths in the network.
Learning Objectives
- Acquire knowledge on tactics used to decrease the length of time required to complete a project, encompassing the idea of "project crashing."
Related questions
Given the Critical Path Below, Calculate the FollowingA ...
If an Activity Whose Normal Duration Is 15 Days Can ...
The Network Below Represents a Project Being Analyzed by Critical ...
Given the Project Within the Table Below CalculateA ...
The Standard Deviation of Project Duration Is the Average of ...