Which of the following statements regarding Gantt charts is true?

A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) Gantt charts identify the critical path.

Gantt Charts

are visual representation tools used in project management to outline the schedule of tasks or activities against a timeline, highlighting dependencies and progress.

Project Activities

Various tasks or actions undertaken to achieve project objectives, including planning, execution, and monitoring.

Critical Path

The longest sequence of tasks in a project that must be completed on time for the whole project to be finished by its deadline, determining the shortest possible project duration.

  • Understand the application and constraints of Gantt charts in depicting project schedules and the connections between activities.
verifed

Verified Answer

RD
Renee D'AngeloMay 10, 2024
Final Answer :
C
Explanation :
Gantt charts are visual devices used to show the duration of each activity in a project. They do not show precedence relationships or use the four standard spines of methods, materials, manpower, and machinery. While they can be created using expensive software, they do not inherently have to be expensive. The critical path is not explicitly identified on a Gantt chart, but can be determined by analyzing the longest path of interconnected activities.