In MRP record calculations, the appearance of a negative value for the gross requirements of an end item in a specific time bucket
A) signals the need to purchase that end item in that period.
B) implies that value was scheduled by the MPS.
C) signals the need for a negative planned order receipt in that period.
D) is impossible.
E) is considered to be equal to zero.
Negative Value
Refers to quantities or numbers less than zero, often indicating a loss, deficit, or something that detracts from a total.
Gross Requirements
The total amount of materials or components needed to manufacture a product or meet demand before considering any existing inventory.
MRP Record Calculations
Computations involved in Material Requirements Planning, a systematic approach to planning, scheduling, and inventory control to manage manufacturing processes.
- Perceive the value of accurately orchestrating time-phased schedules in Material Requirements Planning.
Verified Answer
WA
William AdamsMay 15, 2024
Final Answer :
D
Explanation :
A negative value for the gross requirements of an end item in a specific time bucket is impossible in MRP record calculations because gross requirements represent the total demand for an item, and demand cannot be negative.