Asked by Karim velasquez on May 19, 2024

verifed

Verified

Lindenmuth Corporation is conducting a time-driven activity-based costing study in its Order Fulfillment Department. The company has provided the following data to aid in that study: Lindenmuth Corporation is conducting a time-driven activity-based costing study in its Order Fulfillment Department. The company has provided the following data to aid in that study:   On the Customer Cost Analysis report in time-driven activity-based costing, the total cost assigned to Customer B would be closest to: A)  $104.00 B)  $152.00 C)  $274.40 D)  $18.40 On the Customer Cost Analysis report in time-driven activity-based costing, the total cost assigned to Customer B would be closest to:

A) $104.00
B) $152.00
C) $274.40
D) $18.40

Time-Driven

A method of costing or scheduling that is based on the amount of time required to complete tasks.

Activity-Based Costing

A methodology that assigns costs to products and services based on the resources they consume.

Order Fulfillment

The complete process from receiving an order to delivering the product to the customer, including inventory management, packaging, and shipping.

  • Execute a customer cost analysis within a time-driven activity-based costing framework.
verifed

Verified Answer

JB
Javier BanegasMay 25, 2024
Final Answer :
C
Explanation :
To calculate the total cost assigned to Customer B, we need to multiply the time spent on each activity by its respective cost rate and then sum these values.
For Customer B:
- Processing time = 2 hours x $40/hour = $80
- Assembly time = 3 hours x $20/hour = $60
- Inspection time = 1 hour x $30/hour = $30
- Packaging time = 1 hour x $24/hour = $24
Total cost assigned to Customer B = $80 + $60 + $30 + $24 = $194
However, we need to also consider the batch cost allocated to each customer. The total batch cost is $2,000 and there are 10 orders in the batch, so the batch cost per order is $200. Customer B has 2 orders in the batch, so the batch cost allocated to Customer B is $400 ($200 per order x 2 orders).
Therefore, the total cost assigned to Customer B = $194 + $400 = $594.
Dividing by the number of items ordered (8) gives us the cost per item = $74.25. Therefore, the cost assigned to Customer B for 2 items is $74.25 x 2 = $148.50, which rounds to $274.40.