Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week. The lead time for the manufacture of Y is 1 week. The lead time for the procurement of Z is 6 weeks. The cumulative lead time for X is ________ weeks.
A) 6
B) 7
C) 8
D) 10
E) cannot be determined
Cumulative Lead Time
The total time required to manufacture a product, including the time to procure all necessary materials and components.
Component Y
A hypothetical or specific part of a larger system or machine, typically referred to in the context of manufacturing, assembly, or engineering projects.
Part Z
A hypothetical or specific component within a larger system or product, often used to discuss or analyze a particular aspect of a process or design.
- Comprehend the concept of lead times and their impacts on the scheduling of production and procurement.
Verified Answer
MB
Monserrat BieberMay 25, 2024
Final Answer :
C
Explanation :
To assemble one X, 2 Ys are required, and for each Y, 4 Zs are required. So to assemble one X, 8 Zs are required.
Lead time for X = 1 week
Lead time for Y = 1 week
Lead time for Z = 6 weeks
Therefore, the total lead time for one X = 1 (assembly) + 1 (manufacture of Y) + 6 (procurement of Zs) = 8 weeks.
Lead time for X = 1 week
Lead time for Y = 1 week
Lead time for Z = 6 weeks
Therefore, the total lead time for one X = 1 (assembly) + 1 (manufacture of Y) + 6 (procurement of Zs) = 8 weeks.
Learning Objectives
- Comprehend the concept of lead times and their impacts on the scheduling of production and procurement.