Asked by Michelle Rebollar on May 29, 2024
Verified
Assuming one answer only can be chosen, which of the following is a non-value-added activity for a manufacturing firm?
A) Machining a metal plate in the factory.
B) Packing finished product into cartons for delivery.
C) Moving partly finished production to storage.
D) Inserting a warranty-card and instruction booklet into the boxed product.
Non-Value-Added Activity
Processes or tasks that consume resources but do not add value or enhance the product or service from the customer's perspective.
Partly Finished Production
Items or goods that have undergone some stages of the production process but are not yet complete.
- Establish and discriminate between activities that provide value and those that do not.
Verified Answer
ZK
Zybrea KnightJun 04, 2024
Final Answer :
C
Explanation :
Moving partly finished production to storage does not add any value to the product and only adds to the cost of production. The other activities listed involve directly adding value to the product, such as machining the metal plate, packing the finished product, and providing a warranty-card and instruction booklet for the customer.
Learning Objectives
- Establish and discriminate between activities that provide value and those that do not.
Related questions
Which of the Following Time Drivers Contribute to Non-Value-Added Activities ...
Which of the Following Activities Are Non-Value-Added Activities ...
___ Activities Do Not Add Value Directly to the Firm's ...
Inspection Time Is Generally Considered to Be Value-Added Time
Particular to Corporate Social Responsibility,public Relations Professionals Must Plan Activities ...