After looking at the PERT chart for the development of the new fashion line,Quinn realized that the longest path showed that the project would take a minimum of 60 days.Quinn was able to get this information as a result of the:
A) longest path method.
B) activity path method.
C) critical path method.
D) project path method.
Critical Path Method
A project management technique for determining the longest sequence of dependent tasks and scheduling resources to optimize achievement of project objectives.
PERT Chart
A project management tool used to schedule, organize, and coordinate tasks within a project, standing for Program Evaluation and Review Technique.
Longest Path
In project management, the sequence of tasks that determines the minimum timeframe required to complete a project, with any delay in these tasks delaying the whole project.
- Strengthen abilities in formulating and scrutinizing Gantt and PERT charts.
Verified Answer
Learning Objectives
- Strengthen abilities in formulating and scrutinizing Gantt and PERT charts.
Related questions
A Project Management Tool That Helps Identify Sequences of Dependent ...
In Order to Track Their Progress,Sharon's Team Developed a Chart ...
Lori Developed a PERT Chart That Showed Her the Longest ...
Develop a Gantt Chart for a Team Project for Work ...
Before Beginning the New Project,William Wants to Develop a Diagram ...