The term _____ refers to the budgeted cost of work scheduled that has been done.

Budgeted Cost

The estimated financial expenditure allocated for a project, activity, or operation based on planned activities and resources.

Work Scheduled

A detailed plan that outlines the tasks, timelines, and resources required to complete a project or job.

  • Comprehend the significance of budgeted cost of work scheduled (BCWS) and its application in project tracking.
verifed

Verified Answer

BH
Brandon HerreraJun 10, 2024
Final Answer :
budgeted cost of work performed BCWP)