Asked by Yelyzaveta Vakhtina on Jun 09, 2024

verifed

Verified

_____ will ensure that slack is built into the schedule to accommodate the unexpected,such as incompatibility with previous hardware,heavier than usual sales,or vacations and holidays.

A) Prioritizing resources
B) Long-term objectives
C) Anticipating contingencies
D) Consistent output

Slack

The amount of leeway or extra capacity available within a system, which can accommodate delays or unforeseen issues without impacting the outcome.

Anticipating Contingencies

The process of preparing for potential future events or situations, especially unexpected ones, in planning or decision-making.

Incompatibility

The state of being unable to exist or work together in harmony due to differences in characteristics or purposes.

  • Comprehend the significance of planning for potential obstacles and adding extra time into project plans to improve preparedness.
verifed

Verified Answer

SB
Sonia BhardwajJun 13, 2024
Final Answer :
C
Explanation :
Anticipating contingencies refers to being prepared for unexpected events and building slack into the schedule to accommodate them. Prioritizing resources and long-term objectives are not specific to planning for contingencies, while consistent output does not address the need for flexibility in scheduling.