Which of the following indicates that a project is behind schedule?
A) A SPI value less than one
B) A SPI value more than one
C) A SPI value equal to one
D) A negative CV
E) A positive CV
SPI Value
The Schedule Performance Index, a measure used in project management to compare the work performed against the work scheduled.
- Familiarize yourself with the introductory teachings and applications of Earned Value Management (EVM) for project performance tracking.
Verified Answer
TH
Truong HoangJun 24, 2024
Final Answer :
A
Explanation :
A SPI value less than one indicates that the project is behind schedule, as this means that the project is not progressing as planned in terms of its schedule. A SPI value of one indicates that the project is on schedule, while a value greater than one means that the project is ahead of schedule. CV, on the other hand, measures the cost performance of the project, so it does not directly reflect whether the project is behind schedule or not.
Learning Objectives
- Familiarize yourself with the introductory teachings and applications of Earned Value Management (EVM) for project performance tracking.
Related questions
At the End of Three Months, the Cost Factors in ...
_____ Refers) to Decisions Based on Incomplete Information Made by ...
If the Company That Is Providing the Project Management Is ...
The _____ Is a Project Management Tool That Describes the ...
In Order to Track Their Progress,Sharon's Team Developed a Chart ...