The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are

A) 115.
B) 175.
C) 240.
D) 690.
E) 700.

Net Requirements

The actual amount of materials or products needed to meet demand, after accounting for current inventory levels and scheduled supply receipts.

Part C

In specific contexts, this can refer to a section or segment of a larger document, plan, or legislation, detailing specific aspects or requirements.

  • Acquire the ability to determine net requirements for components by analyzing inventory levels and product demand.
verifed

Verified Answer

IL
Ismaelite Laurore7 days ago
Final Answer :
A
Explanation :
The total requirement for C from Product A is 50 units * 2 = 100 units. For Product B, the net requirement is (60 units - 25 units on hand) * 5 = 35 units * 5 = 175 units. The total requirement for C is 100 units (from A) + 175 units (from B) = 275 units. Given that there are 160 units of C available, the net requirements for C are 275 units - 160 units = 115 units.