Asked by Jamie PARKER on Jul 11, 2024

verifed

Verified

In a process cost system, the cost of completed production in Department 1 is transferred to Department 2 by which of the following entries?

A) debit Work in Process Department 2, credit Work in Process Department 1.
B) debit Finished Goods, credit Work in Process Department 2.
C) debit Work in Process - Department 2, credit Cost of Goods Sold Department 1.
D) debit Work in Process Department 2, credit Finished Goods Department 1.

Process Cost System

An accounting system used to accumulate costs in industries where a homogeneous product is produced on a continuous basis.

Work in Process

Inventory category for items that are currently being produced or in the process of being transformed into finished goods.

  • Comprehend the integration of materials, labor, and overhead expenses in process costing methodologies.
verifed

Verified Answer

CT
Caitlin TomlinsonJul 17, 2024
Final Answer :
A
Explanation :
The correct entry to transfer the cost of completed production from Department 1 to Department 2 in a process cost system is to debit Work in Process Department 2 and credit Work in Process Department 1. This reflects the movement of costs from one production department to the next in the manufacturing process.