Asked by Santiago Quirós on Jul 13, 2024

verifed

Verified

Bret decided to enlarge the fishpond in his backyard. He contracted with a general contractor, Conan. Conan subcontracted with Darson to do the excavation and with Ericson to do the plumbing. Conan's own workers did the masonry work. Bret made "progress payments" to Conan, since Conan said such payments were necessary to pay his workers and subcontractors. Bret learned that the workers and subcontractors had not been paid and Conan had used the payments to pay debts unrelated to the job on Bret's pond. Which of the following best describes Bret's position?

A) Because of the doctrine of privity of contract, Bret will not face any liability whatsoever.
B) If Bret held back the 10% required by statute from his payments to Conan, but then later paid it out despite liens having been filed against his property, Bret would still face no liability as he technically complied with the legislation.
C) Bret will be liable for all unpaid amounts because the work was on his land and for his benefit.
D) If Bret held back the 10% required by statute from his payments to Conan, his obligation would generally be limited to the amount of that holdback.
E) Bret had no obligation to hold back any amount of the payments made to Conan as the hold back requirement doesn't apply to progress payments.

Doctrine of Privity

A legal principle stating that contracts are binding only upon the parties signing them, and no third-party can enforce or be obligated by the contract.

Progress Payments

Payments made through the course of a project or contract based on the completion of specified stages of work.

  • Differentiate the functions and entitlements of conditional sellers, subcontractors, and lien claimants within secured transactions.
  • Comprehend the procedural and legal results as outlined in the Builders' Lien Acts and the Bankruptcy and Insolvency Act.
verifed

Verified Answer

AB
Amber BoeschJul 19, 2024
Final Answer :
D
Explanation :
Bret's obligation to the workers and subcontractors would generally be limited to the amount of the holdback if he complied with the statutory requirement to withhold a percentage of the payment due to the contractor. This is a common provision in construction law to ensure that subcontractors and workers can be paid if the general contractor fails to do so.