Takt time is
A) the total work time available divided by units required by the consumer.
B) the units required divided by workers required.
C) a fictional time increment similar to a therblig.
D) the same thing as cycle time in a process layout.
E) an important consideration in balancing an assembly line.
Takt Time
Pace of production to meet customer demands.
- Comprehend the concepts of takt time and its significance in balancing assembly lines.
Verified Answer
GM
gulsoom muhammadiJul 21, 2024
Final Answer :
A
Explanation :
Takt time is calculated as the total available work time divided by the customer demand or units required by the consumer. It is used as a pacing mechanism to ensure that the production rate matches the customer demand or rate of consumption. Therefore, option A is the correct choice. Option B is incorrect as it calculates the number of workers required, not the pace of production. Option C is also incorrect as it refers to a different concept in industrial engineering. Option D is incorrect as cycle time refers to the time taken to complete one unit of production, whereas takt time refers to the production rate required to meet customer demand. Option E is partially correct as takt time is indeed important in balancing an assembly line, but not the only consideration.
Learning Objectives
- Comprehend the concepts of takt time and its significance in balancing assembly lines.
Related questions
An Assembly Line with 11 Tasks Is to Be Balanced ...
A Firm Is Planning to Set Up an Assembly Line ...
Hemo-Tech, Inc A Draw the Network Diagram of the Precedence ...
A Work Cell Is Required to Make 140 Computerized Diagnostic ...
________ Involves Scheduling Products So That Each Day's Production Meets ...