Using which of the following actions can potential interferences and problems be raised and dealt with before they impact the expected outcomes?
A) By keeping the plan highly visible
B) By arranging ad-hoc meetings
C) By using the conference rooms often
D) By including board level executives
Potential Interferences
Possible disturbances or disruptions that could negatively affect the outcome of an action or process.
Expected Outcomes
Anticipated results or consequences of an action or series of actions.
Highly Visible
Refers to something easily seen or noticed, often implying it attracts much attention or scrutiny.
- Acknowledge the value of early problem detection and solving in the project lifecycle.
Verified Answer
SL
Sabrina LaBranche3 days ago
Final Answer :
A
Explanation :
By keeping the plan highly visible to all stakeholders, potential interferences and problems can be identified early on, discussed and addressed before they impact the expected outcomes.
Learning Objectives
- Acknowledge the value of early problem detection and solving in the project lifecycle.
Related questions
Plotting Interdependencies of Tasks Can Help to Determine Delays or ...
Establishing Checkpoints and Control Mechanisms Can Help You Manage Your ...
By Not Monitoring and Catching Problems Early on in the ...
The Critical Path in a PERT Chart Represents the Tasks ...
Tracey Has Noticed That the Team Is Not Meeting Planned ...