Bill contracts to build a building for Harvey.A few changes in the building code that were made after the contract was signed will increase Bill's costs in performing his duties.He is excused from performance under the contract.

Building Code

Regulations that specify the standards for constructed objects such as buildings and nonbuilding structures, ensuring safety, health, and welfare of the occupants.

Excused from Performance

A legal concept where a party is released from fulfilling their obligations under a contract due to unforeseen circumstances that make performance impossible or impracticable.

  • Examine defences to breach of contract, including impossibility and personal satisfaction.
verifed

Verified Answer

HI
Hellen Iketemabout 19 hours ago
Final Answer :
False
Explanation :
This does not constitute a case of excuse from nonperformance because the performance of the duty is not impossible.It can be performed simply by increasing the costs involved.