Asked by Jackson O'Brien on May 20, 2024
Verified
A document calls for the production of 50 small garden tractors in week 1; 50 small garden tractors and 100 riding mowers in week 2; 100 riding mowers and 200 garden utility carts in week 3; and 100 riding mowers in week 4. This document is most likely a(n)
A) net requirements document.
B) resource requirements profile.
C) aggregate plan.
D) master production schedule.
E) Wagner-Whitin finite capacity document.
Master Production Schedule
A detailed plan that dictates when and how much of each product will be produced over a specific period.
Net Requirements Document
A document that outlines the specific needs and requirements of a project, including materials, resources, and timelines, to ensure its successful completion.
- Attain comprehension regarding master production scheduling and its manifestation in various operational scenarios.
Verified Answer
MJ
Michael JordanMay 24, 2024
Final Answer :
D
Explanation :
The given document outlines the specific production quantities for each week, which is the definition of a Master Production Schedule (MPS).
Learning Objectives
- Attain comprehension regarding master production scheduling and its manifestation in various operational scenarios.
Related questions
In Continuous (Stock-To-Forecast) Operations, the Master Production Schedule Is Usually ...
Which Portion of the Master Production Schedule Is Normally Fixed ...
A Master Production Schedule Contains Information About ...
In Job Shop (Make-To-Order) Operations, the Master Production Schedule Is ...
The ________ Is (Are) the MRP Input Detailing Which End ...