A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
observation: 12345 Task time (seconds): 8274808376\begin{array} { | l | l | l | l | l | l | } \hline \text { observation: } & 1 & 2 & 3 & 4 & 5 \\\hline \text { Task time (seconds): } & 82 & 74 & 80 & 83 & 76 \\\hline\end{array} observation: Task time (seconds): 182274380483576 a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
d. If the analyst then thought more carefully about his experiment, and decided that the variable allowances needed to be increased to match the real (outside, unair-conditioned) work environment, and that the proper variable allowance was not 6% but 12%, what is the revised standard time?
Variable Allowances
Adjustments in time estimates or costs to accommodate changes in work conditions or processes.
Normal Time
The standard duration that a task or activity is expected to take under normal working conditions.
Actual Average Time
The real measured time taken on average to perform a task or process, used in evaluating and planning efficiencies.
- Determine the regular time for assigned operations through the assessment of recorded times and performance rankings.
- Identify the baseline timeframe for operations, taking into account steady and variable allowances.
- Reevaluate standard periods with modified allowances to grasp the consequences of adjustment in allowance values.
Verified Answer
c. Standard time is 94.8 / (1 - .14) = 110.23 seconds. d. The revised standard time is
94.8 / (1 - .20) = 118.5 seconds.
Learning Objectives
- Determine the regular time for assigned operations through the assessment of recorded times and performance rankings.
- Identify the baseline timeframe for operations, taking into account steady and variable allowances.
- Reevaluate standard periods with modified allowances to grasp the consequences of adjustment in allowance values.
Related questions
An Operation in a Television Factory Has an Average Observed ...
Pierceall Corporation Is Conducting a Time-Driven Activity-Based Costing Study in ...
Purchase Allowances Refer to Merchandise a Buyer Acquires but Then ...
The Adjusting Entry to Reflect Inventory Shrinkage Is a Debit ...
The Actual Average Observed Time for a Given Job Is ...