Asked by Lauren Lawlor on May 20, 2024
Verified
A work centre had planned outputs of 10,15,13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. The cumulative deviation in output is
A) 0.
B) 1.
C) -1.
D) 58.
E) unable to determine with given information.
Cumulative Deviation
The sum of differences between observed and expected values, often used in quality control and process monitoring.
Planned Outputs
The expected results or outcomes that are intended to be achieved from a project or initiative.
Actual Outputs
The real and measurable products or results generated by a system or process.
- Acquire knowledge on the approaches for managing inputs and outputs within work-in-process supervision.
Verified Answer
GK
Gilla KavithaMay 21, 2024
Final Answer :
C
Explanation :
The cumulative deviation is calculated by adding up all the deviations between actual and planned outputs.
For the first planned output of 10 hours, the deviation is:
actual output - planned output = 12 - 10 = 2
For the second planned output of 15 hours, the deviation is:
actual output - planned output = 14 - 15 = -1
For the third planned output of 13 hours, the deviation is:
actual output - planned output = 13 - 13 = 0
For the fourth planned output of 20 hours, the deviation is:
actual output - planned output = 18 - 20 = -2
Adding up all the deviations:
2 + (-1) + 0 + (-2) = -1
Therefore, the cumulative deviation is -1, which means that the actual output was 1 hour less than the planned output overall. The correct answer is C.
For the first planned output of 10 hours, the deviation is:
actual output - planned output = 12 - 10 = 2
For the second planned output of 15 hours, the deviation is:
actual output - planned output = 14 - 15 = -1
For the third planned output of 13 hours, the deviation is:
actual output - planned output = 13 - 13 = 0
For the fourth planned output of 20 hours, the deviation is:
actual output - planned output = 18 - 20 = -2
Adding up all the deviations:
2 + (-1) + 0 + (-2) = -1
Therefore, the cumulative deviation is -1, which means that the actual output was 1 hour less than the planned output overall. The correct answer is C.
Learning Objectives
- Acquire knowledge on the approaches for managing inputs and outputs within work-in-process supervision.
Related questions
A Work Centre Is Interested in Limiting Work-In-Process by Not ...
A Method of Input-Output Control That Uses a System of ...
A Work Centre Had Actual Input of 280 Hours and ...
Service Providers Need and Use Operations Management Just as Much ...
Custom Printing Shops and Custom Jewelry Makers Use the Continuous ...