All of the following are techniques project managers can use to accelerate the project schedule, EXCEPT:
A) improving quality.
B) reassigning resources.
C) changing the scope.
D) adding additional resources.
E) using contingency resources
Contingency Resources
Assets or capacities set aside or planned to address potential future events or emergencies in project management.
- Understand the importance of distributing and balancing resources within the realm of project management.
- Determine the techniques and reasoning for expediting a project timeline.
Verified Answer
AA
Abood Abualrob8 days ago
Final Answer :
A
Explanation :
Improving quality may not necessarily accelerate the project schedule as it may require more time and resources to achieve higher quality standards. The other options such as reassigning resources, changing scope, adding additional resources, and using contingency resources are all techniques that can potentially speed up the project schedule.