Asked by Nicole Davis on Sep 26, 2024

Before beginning the new project,William wants to develop a diagram to show all the activities in the project,including their relationship with one another,the interdependence of the activities and the projected time for each activity.William also wants to identify which activities are the most critical for completing the project on time.William should develop a _____ chart.

A) Smith
B) Nolan
C) Gantt
D) PERT

Interdependence of Activities

A situation in which actions or processes are mutually reliant on each other, meaning the outcome of one is affected by the execution of another.

PERT Chart

An application designed for project management to assist in planning, organizing, and managing project tasks.

Critical for Completing

Essential tasks or elements required to successfully finish a project or achieve a goal.

  • Acquire the expertise to construct and decipher Gantt and PERT charts.
  • Examine how project dependencies and contingencies affect project schedules.