Conventional MRP uses time buckets that do not recognize capacity limits, and in fact ignores capacity issues. A more realistic scheduling system that includes work centre capacities and other resource availabilities is

A) aggregate planning.
B) the master production schedule.
C) finite capacity scheduling.
D) the assignment method.
E) level material use.

Finite Capacity Scheduling

A method for planning and scheduling resource allocations and processes, considering the limited availability of these resources.

Time Buckets

A term used in planning and scheduling to represent specific periods of time, such as days, weeks, or months, for organizing activities or data.

MRP

Material Requirements Planning, a system for calculating materials and components needed to manufacture a product.

  • Grasp the importance and application of finite capacity scheduling in realistic scheduling systems.
verifed

Verified Answer

ZK
Zybrea KnightMay 07, 2024
Final Answer :
C
Explanation :
Finite capacity scheduling is a scheduling system that takes into account work centre capacities and other resource availabilities. This creates a more realistic schedule compared to conventional MRP which ignores capacity issues. Therefore, the best choice is C.