Asked by Tyler Lewis on Apr 29, 2024
Verified
Forward scheduling
A) begins with a delivery date, then offsets each operation one at a time, in reverse order.
B) is well suited where the supplier is usually able to meet precise delivery dates.
C) tends to minimize work-in-process inventory.
D) assumes that procurement of material and operations start as soon as requirements are known.
E) produces a schedule only if it meets the due date.
Forward Scheduling
Forward scheduling is a planning method where tasks are scheduled from the start date onwards to determine the earliest possible completion time.
Delivery Date
The specified date on which a product is agreed to be delivered to the customer.
Minimize Work-In-Process Inventory
A strategy to reduce the amount of unfinished goods in production to increase efficiency and decrease waste.
- Understand the principles of forward and backward scheduling and their uses.
Verified Answer
Learning Objectives
- Understand the principles of forward and backward scheduling and their uses.
Related questions
Earliest Due Date Is a Shop Floor Dispatching (Sequencing) Rule ...
Which Scheduling Technique Should Be Employed When Due Dates Are ...
Process-Focused Facilities and Repetitive Facilities Generate Forward-Looking Schedules, but Process-Focused ...
Forward Scheduling Is the Scheduling of ...
In Forward Scheduling, Jobs Are Scheduled as Late as Possible ...