Forward scheduling is the scheduling of
A) the end items or finished products.
B) jobs as soon as the requirements are known.
C) the start items or component parts.
D) the final operation first beginning with the due date.
E) jobs according to their profit contributions.
Forward Scheduling
A planning approach that starts scheduling activities or operations from the earliest possible date and moves forward in time to establish due dates or delivery dates.
End Items
Final products that are completed and ready to be sold or delivered to customers.
Requirements Known
Pertains to a condition where the specifications, needs, or conditions for a project or product are clearly identified and documented.
- Acquire knowledge about the concepts of forward and backward scheduling and their implementation.
Verified Answer
Learning Objectives
- Acquire knowledge about the concepts of forward and backward scheduling and their implementation.
Related questions
Earliest Due Date Is a Shop Floor Dispatching (Sequencing) Rule ...
Which Scheduling Technique Should Be Employed When Due Dates Are ...
Process-Focused Facilities and Repetitive Facilities Generate Forward-Looking Schedules, but Process-Focused ...
Forward Scheduling ...
In Forward Scheduling, Jobs Are Scheduled as Late as Possible ...