Forward scheduling is the scheduling of

A) the end items or finished products.
B) jobs as soon as the requirements are known.
C) the start items or component parts.
D) the final operation first beginning with the due date.
E) jobs according to their profit contributions.

Forward Scheduling

A planning approach that starts scheduling activities or operations from the earliest possible date and moves forward in time to establish due dates or delivery dates.

End Items

Final products that are completed and ready to be sold or delivered to customers.

Requirements Known

Pertains to a condition where the specifications, needs, or conditions for a project or product are clearly identified and documented.

  • Acquire knowledge about the concepts of forward and backward scheduling and their implementation.
verifed

Verified Answer

SH
Samantha HernandezJun 08, 2024
Final Answer :
B
Explanation :
Forward scheduling is the process of scheduling jobs or tasks as soon as the requirements for them are known, starting with the earliest possible start date. This approach is useful when there are limited resources and many jobs to be scheduled, as it ensures that jobs are started as early as possible and that resources are not left idle. Therefore, option B is the correct choice.