If the actual labour hours worked exceed the standard labour hours allowed, what type of variance will occur?
A) Unfavourable labour rate variance.
B) Favourable labour rate variance.
C) Unfavourable labour efficiency variance.
D) Favourable labour efficiency variance.
Labour Efficiency Variance
The difference between the budgeted or standard labor hours expected for production and the actual labor hours used.
Standard Labour Hours
The number of labor hours predetermined as necessary to complete a job or task under normal conditions.
Actual Labour Hours
The actual amount of labor time spent on a particular job or task, measured in hours.
- Ascertain and evaluate fluctuations in labor, with emphasis on rate and efficiency variances.
Verified Answer
JG
julius goddardJul 31, 2024
Final Answer :
C
Explanation :
When actual labour hours exceed the standard hours allowed, it results in an unfavourable labour efficiency variance because more hours were worked than planned, indicating inefficiency.
Learning Objectives
- Ascertain and evaluate fluctuations in labor, with emphasis on rate and efficiency variances.
Related questions
The Labour Rate Variance Is
To Record the Incurrence of Direct Labour Cost and Its ...
Milar Corporation Makes a Product with the Following Standard Costs ...
Fluegge Incorporated Has Provided the Following Data Concerning One of ...
The Following Information Describes Production Activities of the Midtown Corp ...