In a process cost system

A) a Work in Process account is maintained for each product.
B) a materials requisition must identify the job on which the materials will be used.
C) a Work in Process account is maintained for each process.
D) one Work in Process account is maintained for all the processes similar to a job order cost system.

Work In Process Account

An account that tracks the costs associated with partially completed goods in manufacturing processes.

Process Cost System

An accounting method used to track the costs associated with processes that produce homogeneous products.

  • Acquire knowledge on the convergence and divergence between process cost systems and job order cost systems.
verifed

Verified Answer

VB
Victoria BranchJun 14, 2024
Final Answer :
C
Explanation :
In a process cost system, a Work in Process account is maintained for each process. This is because the production process involves a continuous flow of identical or similar units and it is not practical to track individual products or jobs. Therefore, the costs are accumulated for each process and assigned to the units flowing through that process. Option A is incorrect because maintaining a Work in Process account for each product is not practical in a process cost system. Option B is incorrect because materials requisitions are not job-specific in a process cost system. Option D is incorrect because unlike a job order cost system, a process cost system maintains separate Work in Process accounts for each process.