In a process cost system unit costs are determined using a
A) numerator of costs of each job.
B) denominator of units produced during the period.
C) denominator of units produced for the job.
D) denominator of units produced for the day.
Process Cost System
An accounting system used to track costs associated with processes that produce homogeneous products.
Unit Costs
The cost incurred to produce, store, and sell one unit of a product or service.
- Acquire knowledge on the allocation and accounting of production costs in a process costing structure.
Verified Answer
KS
Krystal ScrivensJun 17, 2024
Final Answer :
B
Explanation :
In a process cost system, unit costs are determined by dividing the total production costs by the total number of units produced during the period. Therefore, the denominator used to determine unit costs is the number of units produced during the period, which is choice B.
Learning Objectives
- Acquire knowledge on the allocation and accounting of production costs in a process costing structure.
Related questions
Which of the Following Would Not Appear as a Debit ...
A Product Requires Processing in Two Departments the Baking Department ...
Which of the Following Manufacturing Cost Elements Occurs in a ...
The Total Manufacturing Cost Per Unit Is Used in Costing ...
When Manufacturing Overhead Costs Are Assigned to Production in a ...