Asked by Jessica Tufts on Jun 06, 2024

verifed

Verified

In forward scheduling, jobs are scheduled as late as possible within the time allowed by the customer due dates.

Forward Scheduling

Scheduling that begins the schedule as soon as the requirements are known.

Customer Due Dates

The specified dates by which a product or service must be delivered to the customer, often impacting satisfaction and retention.

  • Grasp the concepts of forward and backward scheduling and their applications.
verifed

Verified Answer

EN
Edgar N. BarrozoJun 11, 2024
Final Answer :
False
Explanation :
In forward scheduling, jobs are scheduled as early as possible from the current date, taking into account the availability of resources and production lead times.