Asked by Haktan Öztürkçü on May 22, 2024

verifed

Verified

Kartman Corporation makes a product with the following standard costs: Kartman Corporation makes a product with the following standard costs:   In June the company's budgeted production was 3,400 units but the actual production was 3,500 units. The company used 22,150 pounds of the direct material and 2,290 direct labor-hours to produce this output. During the month, the company purchased 25,400 pounds of the direct material at a cost of $170,180. The actual direct labor cost was $57,021 and the actual variable overhead cost was $8,931.The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.The variable overhead efficiency variance for June is: A)  $760 Favorable B)  $760 Unfavorable C)  $741 Favorable D)  $741 Unfavorable In June the company's budgeted production was 3,400 units but the actual production was 3,500 units. The company used 22,150 pounds of the direct material and 2,290 direct labor-hours to produce this output. During the month, the company purchased 25,400 pounds of the direct material at a cost of $170,180. The actual direct labor cost was $57,021 and the actual variable overhead cost was $8,931.The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.The variable overhead efficiency variance for June is:

A) $760 Favorable
B) $760 Unfavorable
C) $741 Favorable
D) $741 Unfavorable

Variable Overhead Efficiency Variance

The difference between the actual variable overhead incurred and the standard cost allocated for the actual production achieved.

  • Compute the variances of efficiency and rate in variable overhead to assess the management of overhead costs.
verifed

Verified Answer

EH
Evariste HatungimanaMay 26, 2024
Final Answer :
B
Explanation :
Variable overhead efficiency variance is calculated as follows:

Variable overhead efficiency variance = (Actual hours worked - Standard hours allowed) x Variable overhead rate per hour

Standard hours allowed = Standard direct labor hours per unit x Actual output

Standard direct labor hours per unit = 0.5 hour per unit

Actual output = 3,500 units

Standard hours allowed = 0.5 hour per unit x 3,500 units = 1,750 hours

Variable overhead rate per hour = Actual variable overhead costs ÷ Actual direct labor hours

Variable overhead rate per hour = $8,931 ÷ 2,290 hours = $3.90 per hour

Actual hours worked = 2,290 hours

Variable overhead efficiency variance = (2,290 hours - 1,750 hours) x $3.90 per hour
= $1,711 Unfavorable

Therefore, the answer is B.