Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of 12\frac { 1 } { 2 }21 a day. Each container (kanban) holds 1 cake. What is the correct number of kanbans?
A) not enough information
B) 1
C) 5
D) 10
E) 25
Safety Stock
Additional inventory kept on hand to guard against stockouts caused by uncertainties in demand and lead-time.
Kanbans
A scheduling system for lean manufacturing and just-in-time (JIT) production that signals the need to move materials within a production facility.
- Recognize the crucial elements involved in determining the quantity of Kanbans required for manufacturing and managing inventory.
Verified Answer
CP
Cassie PoulainJul 10, 2024
Final Answer :
E
Explanation :
The correct number of kanbans can be calculated using the formula: Number of Kanbans=Demand during lead time+Safety stockSize of one container \text{Number of Kanbans} = \frac{\text{Demand during lead time} + \text{Safety stock}}{\text{Size of one container}} Number of Kanbans=Size of one containerDemand during lead time+Safety stock . Here, demand during lead time is 2 days×10 cakes/day=20 cakes2 \text{ days} \times 10 \text{ cakes/day} = 20 \text{ cakes}2 days×10 cakes/day=20 cakes , and safety stock is 0.5 day×10 cakes/day=5 cakes0.5 \text{ day} \times 10 \text{ cakes/day} = 5 \text{ cakes}0.5 day×10 cakes/day=5 cakes . Thus, 20 cakes+5 cakes1 cake/container=25 \frac{20 \text{ cakes} + 5 \text{ cakes}}{1 \text{ cake/container}} = 25 1 cake/container20 cakes+5 cakes=25 kanbans.
Learning Objectives
- Recognize the crucial elements involved in determining the quantity of Kanbans required for manufacturing and managing inventory.
Related questions
The Number of Kanbans Should Be Equal to A) One \(\frac ...
Lead Time for Computers Is 5 Days with Daily Demand ...
Lead Time for Computers Is 7 Days with Daily Demand ...
A Kanban System Requires Little Variability in Lead Time Because ...
A Grocery Store Is Attempting to Implement a Kanban System ...