Materials requirement plan (MRP) is most effective at managing independent demand items.

Materials Requirement Plan (MRP)

A system for calculating the materials and components needed to manufacture a product, ensuring the right materials are available for production at the right time.

Independent Demand Items

Products for which demand is not influenced by the demand for other products, typically finished goods or spare parts.

  • Detail the significance of capacity requirements planning (CRP) and materials requirements planning (MRP) in managing production processes.
verifed

Verified Answer

KS
Karanpreet SinghMay 18, 2024
Final Answer :
False
Explanation :
MRP is most effective at managing dependent demand items, as it schedules the production and purchase of components based on the demand of the final product.