Asked by Kiauna Floyd on Jul 24, 2024

verifed

Verified

Patridge Company uses a standard cost system in which it applies manufacturing overhead to units of product on the basis of direct labour-hours. The information below is taken from the company's flexible budget for manufacturing overhead:  Percent of capacity 70%80%90% Direct labour-hours 21,00024,00027,000 Variable overhead $42,000$48,000$54,000 Fixed overhead 108,000108,000108,000 Total overhead $150,000$156,000$162,000\begin{array} { | l | l | l | l | } \hline \text { Percent of capacity } & 70 \% & 80 \% & 90 \% \\\hline \text { Direct labour-hours } & 21,000 & 24,000 & 27,000 \\\hline \text { Variable overhead } & \$ 42,000 & \$ 48,000 & \$ 54,000 \\\hline \text { Fixed overhead } & 108,000 & 108,000 & 108,000 \\\hline \text { Total overhead } & \$ 150,000 & \$ 156,000 & \$ 162,000 \\\hline\end{array} Percent of capacity  Direct labour-hours  Variable overhead  Fixed overhead  Total overhead 70%21,000$42,000108,000$150,00080%24,000$48,000108,000$156,00090%27,000$54,000108,000$162,000 During the year, the company operated at exactly 80% of capacity, but applied manufacturing overhead to products based on the 90% level. The company's fixed overhead volume variance for the year was:

A) $6,000 favourable.
B) $12,000 unfavourable.
C) $12,000 favourable.
D) $6,000 unfavourable.

Flexible Budget

A report showing estimates of what revenues and costs should have been, given the actual level of activity for the period.

Manufacturing Overhead

The sum of all costs involved in the production process other than direct materials and labor, such as utilities and rent for the manufacturing facilities.

Fixed Overhead Volume Variance

The difference between the budgeted and actual volume of units produced, multiplied by the standard fixed overhead rate.

  • Understand the application of standard costs in manufacturing overhead.
verifed

Verified Answer

MA
Michael and Roni SteinmeyerJul 30, 2024
Final Answer :
B
Explanation :
The fixed overhead volume variance is calculated as the difference between the budgeted fixed overhead and the fixed overhead applied based on actual activity. Operating at 80% capacity, the budgeted fixed overhead is $108,000. However, overhead was applied based on the 90% level, which would imply applying $108,000 (fixed overhead does not change with the level of activity within the relevant range). The variance is $0 because fixed overhead is the same regardless of the activity level within the relevant range, indicating an error in the question's premise about calculating the fixed overhead volume variance.