PERT is most appropriate for

A) machine-paced work.
B) assembly-line operations.
C) projects where time is not a major factor.
D) large, non-routine projects.
E) managers who prefer hand calculations.

PERT

Project Evaluation and Review Technique, a project management tool used to plan, schedule, and control complex tasks.

Non-Routine Projects

Projects characterized by high uncertainty, novelty, and complexity, often requiring customized approaches and flexible problem-solving strategies.

  • Recognize the application and functionality of Project Evaluation and Review Technique (PERT) in project management.
verifed

Verified Answer

CC
Czarina Concepcion2 days ago
Final Answer :
D
Explanation :
PERT (Program Evaluation and Review Technique) is best suited for large, non-routine projects which require careful planning, scheduling, and monitoring of various activities that need to be completed within a specific timeframe. PERT helps to identify the critical path, estimate project completion time, and prioritize tasks, making it a valuable tool for project managers dealing with complex and uncertain projects.