Proactive project managers usually rely on their ability to handle unexpected events without prior planning.

Proactive Project Managers

Project managers who anticipate future problems, needs, or changes and act in advance to address them.

  • Understand the proactive vs. reactive approaches in project risk management.
verifed

Verified Answer

JR
James Richards7 days ago
Final Answer :
False
Explanation :
Proactive project managers actually plan for unexpected events by identifying potential risks and developing contingency plans in advance. They anticipate and prepare for potential problems, rather than simply relying on their ability to handle them as they arise.