Product A is made from 2 Bs and 1 C. Lead times for A, B, and C are 2, 3, and 2 weeks respectively. Currently there are 2 Bs and a 5 Cs on hand, with 5 of each scheduled to arrive at the end of week 1. If 20 As are needed during week 4, can the order be completed (it is the start of week 0 currently)?

Lead Times

The amount of time that elapses between the initiation and the completion of a production process or the delivery of a service.

Order Completion

The process of fulfilling customer orders from start to finish including manufacturing, packaging, and shipping.

Product A

A placeholder name for a specific product, often used in examples or cases where the actual product name is not given.

  • Determine the feasibility of completing orders by analyzing the lead time and existing inventory levels.
verifed

Verified Answer

JJ
Jasmine JonesMay 13, 2024
Final Answer :
To produce 20 As requires 40 Bs and 20 Cs at the start of week 2. Since the lead time for B is greater than 2 weeks the order cannot be completed on time.