__________ requires that the planning process include people who will be affected by the resulting plans and/or will be asked to help implement them.

A) Scenario planning
B) Strategic planning
C) Participatory planning
D) Contingency planning
E) Benchmarking

Participatory Planning

A planning approach that involves stakeholders, especially those affected by decisions, in the decision-making process to ensure inclusivity and relevance.

Affected By

Influenced or changed by something; the state of being impacted by external factors or conditions.

Implement

To put into action or execute a plan, decision, or tool, especially in a practical context.

  • Comprehend the advantages and constraints of participatory planning.
verifed

Verified Answer

CH
Corrie Hofford CastleJun 27, 2024
Final Answer :
C
Explanation :
Participatory planning emphasizes the involvement of stakeholders, including those who will be affected by the plans or will have a role in implementing them, ensuring their input and engagement throughout the planning process.