(Table: Costs of Birthday Cakes) Use Table: Costs of Birthday Cakes.Assume that fixed costs are $10.What is the average total cost of 2 cakes?

A) $35.00
B) $25.00
C) $17.50
D) $12.50

Average Total Cost

The cost per unit produced, calculated by dividing the overall production expenses by the total units produced.

Fixed Costs

Fixed Costs are expenses that do not vary with changes in production level or sales volume, such as rent, salaries, and equipment leases.

Birthday Cakes

Custom-decorated or pre-made cakes that are often a central dessert at birthday celebrations.

  • Calculate the averages of total, variable, and fixed costs using the data provided.
verifed

Verified Answer

JL
Jasmine LeighMay 08, 2024
Final Answer :
C
Explanation :
To calculate the average total cost of 2 cakes, we need to add the average variable cost (AVC) to the fixed cost (FC) and then divide by the number of cakes produced.
AVC for 2 cakes = ($20 + $30) / 2 = $25
Total cost for 2 cakes = $25 + $10 = $35
Average total cost for 2 cakes = $35 / 2 = $17.50.
Therefore, the best choice is C.