The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4− B 2 A C 7− D 4 A E 5 B, C, D \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 4 & - \\\hline \text { B } & 2 & \text { A } \\\hline \text { C } & 7 & - \\\hline \text { D } & 4 & \text { A } \\\hline \text { E } & 5 & \text { B, C, D } \\\hline\end{array} Activity A B C D E Duration 42745 Immediate Predecessors − A − A B, C, D
A) A-B-D; 10
B) A-B-E; 11
C) C-E; 12
D) A-D-E; 13
E) A-B-C-D-E; 22
Critical Path
The longest sequence of activities in a project plan that must be completed on time for the project to complete on due date.
Immediate Predecessors
The activities or tasks that directly precede another in a project schedule or process, without any intervening tasks.
Activity Duration
The time period from the start to the end of an activity or task.
- Master the concept and utility of critical path analysis in the orchestration and realization of projects.
Verified Answer
GG
Grace GreenJul 29, 2024
Final Answer :
D
Explanation :
The critical path is the longest path through the network, which determines the shortest time possible to complete the project. Here, the critical path is A-D-E with durations 4 (A) + 4 (D) + 5 (E) = 13.
Learning Objectives
- Master the concept and utility of critical path analysis in the orchestration and realization of projects.
Related questions
A Simple CPM Network Has Three Activities, D, E, and ...
Which of the Following Statements Concerning CPM Activities Is False ...
A Simple CPM Network Has Five Activities, A, B, C ...
Given the Project Within the Table Below CalculateA ...
The Network Below Represents a Project Being Analyzed by Critical ...