Asked by Kevin Wiley Jr. on Apr 27, 2024
Verified
The direct materials in the flexible budget for January would be closest to:
A) $130,599
B) $134,694
C) $130,410
D) $135,084
Direct Materials
Raw materials that can be directly attributed to the production of finished goods, considered a variable cost.
Flexible Budget
A budget that adjusts or flexes with changes in volume or activity, allowing companies to better forecast costs and revenues.
- See and measure a variety of spendings and income in both fixed and elastic budgets.
- Discern the involvement of direct labor, direct materials, and specific budgetary items in the planning of finances.
Verified Answer
KB
Kimberly BradwayApr 29, 2024
Final Answer :
A
Explanation :
Cost = Fixed cost + (Variable cost per unit × q)
= $0 + ($18.90 × 6,910)= $130,599
= $0 + ($18.90 × 6,910)= $130,599
Learning Objectives
- See and measure a variety of spendings and income in both fixed and elastic budgets.
- Discern the involvement of direct labor, direct materials, and specific budgetary items in the planning of finances.
Related questions
The Total Expenses in the Flexible Budget for October Would ...
The Amount Shown for Total Expenses in the Planning Budget ...
The Amount Shown for Other Expenses in the Planning Budget ...
The Amount Shown for Servicing Materials in the Planning Budget ...
The Amount Shown for Refurbishing Materials in the Planning Budget ...