The estimated total manufacturing overhead for the Assembly Department is closest to:
A) $77,600
B) $101,600
C) $56,674
D) $24,000
Estimated Total Manufacturing Overhead
The projected total of all indirect costs involved in manufacturing over a specific period.
- Determine the overall manufacturing overhead for distinct departments.
Verified Answer
CU
Corine Ungaretti7 days ago
Final Answer :
B
Explanation :
Assembly Department overhead cost = Fixed manufacturing overhead cost + (Variable overhead cost per direct labor-hour × Total direct labor-hours in the department)
= $77,600 + ($3.00 per direct labor-hour × 8,000 direct labor-hours)
= $77,600 + $24,000 = $101,600
= $77,600 + ($3.00 per direct labor-hour × 8,000 direct labor-hours)
= $77,600 + $24,000 = $101,600
Learning Objectives
- Determine the overall manufacturing overhead for distinct departments.
Related questions
Dallman Corporation Uses a Job-Order Costing System with a Single ...
Petty Corporation Has Two Production Departments, Milling and Finishing ...
Garza Corporation Has Two Production Departments, Casting and Customizing ...
Marciante Corporation Has Two Production Departments, Casting and Finishing ...
The Amount of Overhead Applied in the Forming Department to ...