Asked by Richard Cutshaw on May 19, 2024

verifed

Verified

The ________ is (are) the MRP input detailing which end items are to be produced, when they are needed, and in what quantities.

A) master production schedule
B) load report
C) inventory records
D) assembly time chart
E) bill of material

Master Production Schedule

A plan for individual commodities to be produced in each period which serves as a company's backbone in creating an operational schedule.

Assembly Time Chart

A graphical representation that shows the sequence and duration of operations required to assemble a product.

Bill Of Material

A comprehensive list detailing all the materials, parts, and components required to produce a finished product.

  • Absorb information on master production scheduling and observe its usage in multiple operational settings.
verifed

Verified Answer

NA
Nahia AkterMay 21, 2024
Final Answer :
A
Explanation :
The master production schedule (MPS) is the MRP input that details which end items are to be produced, when they are needed, and in what quantities. The MPS is used to drive the rest of the MRP process, which includes generating material requirements and creating production schedules. The other options are not directly related to this task.