The labor efficiency variance for September is:
A) $1,540 F
B) $1,687 U
C) $1,687 F
D) $1,540 U
Labor Efficiency Variance
The difference between the actual labor hours worked and the standard labor hours expected for the level of production achieved, multiplied by the standard labor rate.
September
The Gregorian calendar's ninth month.
- Master the approach to calculating and interpreting deviations in labor efficiency.
Verified Answer
PM
Papango, Mary GraceJun 11, 2024
Final Answer :
A
Explanation :
SH = 2,500 units × 0.7 hours per unit = 1,750 hours
Labor efficiency variance = (AH - SH)× SR
= (1,680 hours ? 1,750 hours)× $22.00 per hour
= (?70 hours)× $22.00 per hour
= $1,540 F
Labor efficiency variance = (AH - SH)× SR
= (1,680 hours ? 1,750 hours)× $22.00 per hour
= (?70 hours)× $22.00 per hour
= $1,540 F