The labor rate variance for May is:

A) $6,460 U
B) $6,118 U
C) $6,118 F
D) $6,460 F

Labor Rate Variance

The difference between the actual labor costs incurred and the expected (or standard) labor costs for the production achieved.

May

Not a term that needs defining within the given context.

  • Examine and understand variations in labor rate discrepancies.
verifed

Verified Answer

MB
Miles BridgettApr 29, 2024
Final Answer :
C
Explanation :
Labor rate variance = (AH × AR)− (AH × SR)
= (3,220 hours × $22.10 per hour)− (3,220 hours × $24.00 per hour)
= $71,162 − $77,280
= $6,118 F
Reference: CH09-Ref61
Wolery Inc.has provided the following data concerning one of the products in its standard cost system. Labor rate variance = (AH × AR)− (AH × SR) = (3,220 hours × $22.10 per hour)− (3,220 hours × $24.00 per hour) = $71,162 − $77,280 = $6,118 F Reference: CH09-Ref61 Wolery Inc.has provided the following data concerning one of the products in its standard cost system.   The company has reported the following actual results for the product for April:  The company has reported the following actual results for the product for April: Labor rate variance = (AH × AR)− (AH × SR) = (3,220 hours × $22.10 per hour)− (3,220 hours × $24.00 per hour) = $71,162 − $77,280 = $6,118 F Reference: CH09-Ref61 Wolery Inc.has provided the following data concerning one of the products in its standard cost system.   The company has reported the following actual results for the product for April: