The longest path to the completion of the project is called the _____.
A) critical path
B) project logic diagram
C) milestone schedule
D) work breakdown structure
E) scope of work
Project Logic Diagram
A visual representation of the logical sequencing of activities, tasks, and milestones required to achieve a project's objectives.
Milestone Schedule
A project management tool that outlines significant events or achievements as specific points along a project timeline.
Work Breakdown Structure
A hierarchical decomposition of a project into smaller components and work packages, making project management more manageable.
- Gain insight into the concepts of critical path, total float, and project duration.
Verified Answer
Learning Objectives
- Gain insight into the concepts of critical path, total float, and project duration.
Related questions
Given the Project Within the Table Below CalculateA ...
The Network Below Represents a Project Being Analyzed by Critical ...
A Simple CPM Network Has Five Activities, A, B, C ...
A Simple CPM Network Has Three Activities, D, E, and ...
Which of the Following Statements Concerning CPM Activities Is False ...