The most appropriate sequencing rule to use if the goal is to dynamically track the progress of jobs and establish relative priority on a common basis is

A) shortest processing time.
B) earliest due date.
C) critical ratio.
D) longest processing time.
E) Johnson's rule.

Sequencing Rule

A set of guidelines or methods used to determine the order in which tasks or operations should be performed to optimize efficiency and outcomes in production or project management.

Critical Ratio

A metric used in inventory management and project scheduling that indicates the priority of a task based on its urgency and importance.

Relative Priority

The ranking or importance of tasks or projects in comparison to each other based on criteria such as urgency or impact.

  • Discern between distinct sequencing rules and their utilization to decrease the duration of job flow and increase operational efficiency.
verifed

Verified Answer

AJ
Alexis JohnsonMay 06, 2024
Final Answer :
C
Explanation :
The critical ratio rule takes into account the remaining processing time and the time until the due date, allowing for a flexible approach to sequencing based on the progress of jobs. This rule ensures that jobs with the highest priority are completed first, while also taking into consideration the time remaining until the due date. Therefore, it is the best choice for dynamically tracking the progress of jobs and establishing relative priority on a common basis.