Asked by Lizbeth Longoria on Jul 02, 2024
Verified
The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are
A) 115.
B) 175.
C) 240.
D) 690.
E) 700.
Net Requirements
The actual amount of materials or products needed to meet demand, after accounting for current inventory levels and scheduled supply receipts.
Part C
In specific contexts, this can refer to a section or segment of a larger document, plan, or legislation, detailing specific aspects or requirements.
- Acquire the ability to determine net requirements for components by analyzing inventory levels and product demand.
Verified Answer
IL
Ismaelite Laurore7 days ago
Final Answer :
A
Explanation :
The total requirement for C from Product A is 50 units * 2 = 100 units. For Product B, the net requirement is (60 units - 25 units on hand) * 5 = 35 units * 5 = 175 units. The total requirement for C is 100 units (from A) + 175 units (from B) = 275 units. Given that there are 160 units of C available, the net requirements for C are 275 units - 160 units = 115 units.
Learning Objectives
- Acquire the ability to determine net requirements for components by analyzing inventory levels and product demand.
Related questions
The MPS Calls for 110 Units of Product A ...
Incidental Costs for Acquiring Merchandise Inventory,such as Import Duties,freight,storage,and Insurance,should ...
The Cost of Goods Purchased During a Period Plus the ...
If the Unit Cost of Inventory Has Continuously Increased the ...
Two Widely Used Methods of Estimating Inventories Are the ______________ ...