Asked by Krystina Edwards on May 27, 2024
Verified
The path with the least time-consuming chain of activities is the critical path through a PERT network.
Critical Path
The sequence of stages determining the minimum time required to complete a project, highlighting the most important tasks that need timely completion.
- Examine the efficacy of diverse instruments and strategies utilized in the planning and decision-making process.
Verified Answer
AS
ARSHDEEP SINGHJun 01, 2024
Final Answer :
False
Explanation :
The critical path through a PERT (Program Evaluation and Review Technique) network is the sequence of activities that represents the longest path through a project, which determines the shortest possible duration to complete the project.
Learning Objectives
- Examine the efficacy of diverse instruments and strategies utilized in the planning and decision-making process.
Related questions
Facebook Founder, Mark Zuckerberg, Used ____________ as One of His ...
A Project to Build Three Customized Golf Carts Is a ...
For Large, Non-Routine Projects, Program Evaluation and Review Technique (PERT) ...
When a Project or Activity Is Budgeted in Each New ...
__________ Identifies Alternative Future Scenarios and Makes Plans to Deal ...