The path with the least time-consuming chain of activities is the critical path through a PERT network.

Critical Path

The sequence of stages determining the minimum time required to complete a project, highlighting the most important tasks that need timely completion.

  • Examine the efficacy of diverse instruments and strategies utilized in the planning and decision-making process.
verifed

Verified Answer

AS
ARSHDEEP SINGHJun 01, 2024
Final Answer :
False
Explanation :
The critical path through a PERT (Program Evaluation and Review Technique) network is the sequence of activities that represents the longest path through a project, which determines the shortest possible duration to complete the project.