Asked by Jessica Redding on Apr 25, 2024

verifed

Verified

The priority rule that sequences jobs using the smallest ratio of due date from today to processing time is

A) critical ratio.
B) earliest due date.
C) first come, first served.
D) longest processing time.
E) shortest processing time.

Critical Ratio

A scheduling or prioritization technique that calculates the ratio of the time remaining until a task's due date to the time required to complete the task, used to order tasks by urgency.

Due Date

The specified date by which a task, project, or payment is required to be completed or submitted.

Priority Rule

A guideline or criterion used to determine the sequence in which tasks or operations will be carried out in a process or system.

  • Fathom and acknowledge the assortment of regulations for scheduling and sending out jobs.
  • Discriminate between diverse sequencing strategies and their employment to diminish the length of job processing and boost efficiency.
verifed

Verified Answer

AZ
Anastasiia ZotovaMay 01, 2024
Final Answer :
A
Explanation :
The critical ratio rule takes into account the due date of the job and the processing time to determine which jobs should be prioritized. This rule is often considered the most effective method for scheduling jobs as it prioritizes those jobs that are closest to their due date and require less processing time.